The sample room is a queue before it is a room
In a peak week the room holds more styles than the floor can knit in a day. Each style that arrives with a brief is a job with a start, a stop and a next stop.
That stop ahead of you is not idle time. Yarn is pulled, a swatch is knitted, someone looks at it, and only then does the sample go on a machine. A round we quote at 3–5 days assumes the yarn sits in stock and the artwork is final.
Source: our sampling to bulk timeline, which runs the same steps in order.
A new yarn or a new color card takes a slot of its own
A style that reuses a yarn on the creel and a color already carded starts inside the standard window. A style that needs a new yarn opens a slot of its own: the yarn comes in, the machine knits a swatch, and a person looks at it before the sock is knitted.
A color card we have to match works the same way. A Pantone number is a target, not a yarn. Our walkthrough on Pantone to yarn color matching sets out that order.
So two briefs that land the same morning can leave the room four days apart.
Source: our Pantone to yarn color matching walkthrough, and the material briefings that name the yarns we knit often.
The round starts when the brief and the artwork are both in hand
The clock on a sample round does not start when the email arrives. It starts when a brief we can knit from and artwork we can print from are both in the room.
What counts as a brief in hand:
- A construction in percentages, not a yarn name.
- The sample size, in centimeters.
- A color reference, as a Pantone number or a physical swatch.
- The end use, so the cylinder count is chosen before the yarn is pulled.
- Artwork as a file at print size, with the placement named.
A logo sent as a screenshot comes back a day later as a question about print size.
Source: our sample policy, which states the fee and what starts a round.
Day by day, what one sample round looks like
| Day | What the room does | What the buyer receives |
|---|---|---|
| Day 0 | Brief and artwork are logged together and the style takes a queue slot. | A confirmation with the slot and the fee. |
| Day 0–1 | The desk answers counter-questions on construction, color and size. | One email with the open points. |
| Day 1–2 | Yarn is pulled and the color card is matched to the reference. | The yarn reference we matched. |
| Day 2–3 | The sample is knitted on the cylinder the end use calls for. | Machine photos, if the brief asked. |
| Day 3 | The pair is knitted, toe linked and boarded: the sock is closed and shaped to size. | The stop most buyers forget to plan for. |
| Day 4–5 | The sample is labeled, packed and booked with the courier. | A tracking number and the freight cost. |
Source: our sampling to bulk timeline, whose round, day by day, runs these stops in this order.
What moves a sample round, and by how many days
Two lines below sit on the buyer's side of the email, and they cost the most days.
| What changes | What the room does | Days it adds |
|---|---|---|
| A yarn we hold in stock | Pulled and carded in the standard slot. | 0 |
| A new yarn | Brought in, swatched and checked before knitting. | 2–3 |
| A color matched from a swatch | Card matched, then checked against the knitted sock. | 1–2 |
| A second round after a change | A new place in the queue, where it lands. | 3–5 |
| Artwork redrawn after round one | The file is reworked and the sock re-knitted. | 2–4 |
| Merino on the construction | Held as a yarn; the construction adds a round. | 3–5 |
A second round does not restart at day one. It restarts at the queue, at whatever place the style lands. Two rounds double a sample calendar.
Source: our note on sampling from brief to approved sample, which prices the round and the credit.
Approving on a screen moves the problem into bulk
A photograph confirms that the style exists. It is a poor way to approve it. Color shifts with the panel and with file compression, and the drape of a 78 / 20 / 2 blend does not read in a still.
Approve from a screen and the first time anybody holds the sock is after the bulk run is on the machine.
A photograph is quick to look at. A bulk run already knitted takes a good deal longer to take back.
Source: our QC checklist, which starts every inspection from the approved sample.
What to put in writing before the round starts
The desk can date a round on the day the brief and the artwork are both in hand. These six lines hold that date.
- The construction in percentages, with the blend as numbers.
- The sample size in centimeters, and whether you want one size or three.
- The color reference in Pantone, plus a swatch for a critical color.
- Artwork as a file at print size, with the placement named.
- The end use, so the cylinder count is settled before the yarn is pulled.
- A named person on your side who can approve in one round.
The fee is USD 30–80 per style, credited against the first bulk order, with the courier on the buyer's account.
Source: our quote page, where the round, the fee and the slot are confirmed.
- Our own sampling to bulk timeline — the steps in this post, in order.
- Our own sample policy — the USD 30–80 per style fee and the credit.
- Our own lead time page — the 20–30 day bulk window after approval.
- Our own Pantone to yarn color matching walkthrough — a reference into a yarn.
- Our own MOQ page — the 1,000 pair minimum, stated per style.